SCOPE OF
TEST CODE #28 – PLUMBING
PERCENT OF TEST:
37% Plumbing and Gas Codes and Laws
21 % Plumbing Related Mathematics
13 % Related Science
18 % Industry Knowledge
5 % Blueprint Knowledge
6 % Safety
THE WRITTEN EXAMINATION IS ALIGNED
WITH THE MATCHING
You may refer
to http://www.doe.mass.edu/cte/frameworks
for the Massachusetts Vocational Technical Educator Frameworks.
THE
FOLLOWING LIST OF REFERENCE MATERIALS WAS DEVELOPED AS A GUIDE
FOR
WRITTEN EXAM CANDIDATES:
Published
by The Office of the Massachusetts Secretary of State
BUILDING
TRADES PRINT READING-Part 3
ISBN
0-8269-0455-6
OSHA
REGULATIONS (Safety)
MODERN
PLUMBING, Blankenbaker, Keith E.
Published
by Goodheart-Willcox Co.
ISBN
1-59070-350-2
SCOPE OF
TEST CODE #28 – PLUMBING
-Page 2-
MATHEMATICS
FOR PLUMBERS AND PIPERFITTERS, 5th Edition
Published
by Delmar Publishers
ISBN
0-8273-7061-X
YOU
MAY WANT TO CHECK WITH YOUR LOCAL LIBRARY FOR OBTAINING THESE RESOURCES THROUGH
THE INTERLIBRARY LOAN PROGRAM.
The written exam consists of 100 multiple
choice questions. Each question consists
of one incomplete sentence or a questions followed by four choices. Listed below are several sample items:
What
is the total pressure on a 4" diameter test plug in a stack with a head of
20 feet?
a. 58
lbs.
b. 75
lbs.
c. 97
lbs.
* d. 109
lbs.
When
working in a trench which is four or more feet in depth, a ladder or steps
shall be provided and located so as to require no more than ______________ fee
of lateral travel.
a. 5
* b. 25
c. 50
d. 75
* indicates
correct answer
THE TEACHER
TESTING PROGRAM WILL PROVIDE NON-PROGRAMMABLE CALCULATORS FOR USE IN COMPLETING
THE WRITTEN EXAM. DOCUMENTATION REGARDING THESE CALCULATORS WILL BE INCLUDED IN
YOUR ADMISSION PACKAGE.
UPDATED: 7/2008
SCOPE OF TEST CODE #28 – PLUMBING
PERCENT
OF TEST:
33 1/3% PVC-PROJECT
-Construct
a basic plumbing installation using
1 ½" PVC pipe and fittings, showing all
math.
33 1/3% NO-HUB CAST IRON PROJECT
-Construct
a basic piping installation using 2"
pipe and fittings with Tyler No Hub
couplings,
showing all math.
33 1/3% COPPER TUBING PROJECT
-Construct
a ½" copper tubing project using ½"
copper
tubing and 95/5 solder, showing all math.
GRADING
CRITERIA FOR ABOVE PROJECTS:
|
MEASUREMENT
ACCURACY |
TEST |
|
ALIGNMENT |
TIME |
|
NEATNESS |
SAFETY |
|
MATHEMATICAL
COMPUTATION |
STOCK LIST |
ALL CANDIDATES FOR THE
PLUMBING PERFORMANCE EXAMINATION SHOULD WEAR APPROPRIATE WORK CLOTHES FOR THE
CONSTRUCTION INDUSTRY.
CANDIDATE IS RESPONSIBLE FOR SUPPLYING
THE FOLLOWING:
Six-foot Rule or Tape Measure
Pocket Knife or Reamer for 1 ½ "
PVC
Pencil
Safety Glasses
SAFETY
SHOES MUST BE WORN.
You may refer
to http://www.doe.mass.edu/cte/frameworks
for the Massachusetts Vocational Technical Educator Frameworks.
CANDIDATES ARE REMINDED
THAT THE USE OF A CALCULATOR IS
ALLOWED
FOR THE PERFORMANCE EXAM PROVIDING YOU BRING YOUR OWN.
UPDATED: 7/2008